Safer, Better Streets - Goldstone Villas Roundabout

We’re looking to improve the Goldstone Villas roundabout as part of our Safer, Better Streets programme.

Every year we assess requests for safety improvements all over the city, using our 'Safer, Better Streets’ assessment process.

The proposals for this scheme focus on the crossroads on Goldstone Villas, Eaton Villas and Clarendon Villas where there is currently a mini roundabout.

The proposed improvements to the layout include:

  • Removing the mini roundabout
  • Creating a raised junction to reduce speeds
  • Installing give-way instruction lines on Clarendon Villas at the junction with Goldstone Villas
  • Widening the pavements on Eaton Villas and Clarendon Villas at the junctions to create more space for pedestrians
  • Making the junction of Eaton Villas and Goldstone Villas one way for motor vehicles
  • Improving the pedestrian crossing point on Eaton Villas
  • Adding a new crossing point across Goldstone Villas
  • Upgrading the current crossing on Clarendon Villas to a zebra crossing

We want to hear your views

The survey is open until 2 September 2024 and should take no more than 5 minutes to complete.

You can find more information on our Safer, Better Streets webpage, including how you can request a road safety improvement.

You're viewing real-time data. Participant counts are continuously updated for administrators. Please note that regular users see cached data, which may result in slight differences in the numbers.
89 participants

Phases

Phases overview

Implementation phase

31 March 2025 - No end date

The work is due to start on Monday 3rd November 2025 and are expected to last for approximately 6 weeks.

The improvements aim to support safer journeys for pedestrians by making roads and junctions easier to navigate and more accessible.


Works include:

·        Removing the mini roundabout and raising the junction on the approach to encourage vehicles to slow down

·        Making the junction of Eaton Villas and Goldstone Villas one way for motor vehicles

·        Installing give-way lines on Clarendon Villas at the junction with Goldstone Villas

·        Widening the pavements on Eaton Villas and Clarendon Villas at the junctions to create more space for pedestrians

·        Improving the pedestrian crossing on Eaton Villas

·        Adding a new crossing point across Goldstone Villas

·        Upgrading the current crossing on Clarendon Villas to a zebra crossing


All diversion routes will be clearly signposted. Residents and businesses within the closure will still retain access to their properties. On-street parking may be temporarily restricted.